Key takeaway
Exact boundaries vary by contract and project philosophy. The key is to define systems, acceptance criteria, responsibilities and turnover dossiers before construction ends.
Control points
Mechanical Completion: construction completed with inspections and punch status per project criteria.
Turnover: documented transfer of a system or subsystem to the next responsible team.
Pre-Commissioning: cleaning, flushing, tests, rotation checks, loop checks and defined preparation.
Commissioning: functional tests, sequences, interlocks and operating demonstration.
Start-Up: controlled introduction of operating conditions and progressive ramp-up.
Common mistakes
Frequently asked questions
Does Mechanical Completion mean equipment can start?
Not necessarily. It usually confirms completion of the construction scope against project criteria, while pre-commissioning and commissioning activities remain.
Who defines turnover criteria?
The contract, commissioning philosophy and project procedures should define criteria and responsibilities.
Do punch items always block turnover?
It depends on category and project rules. Critical safety or function items may block a gate while lower-priority items may be carried forward.